Processing plant


Fuyuan tea industry

In October 2023, it was rated as a 3A scenic spot for Fuyuan tea tour integration.

Fuyuan tea industry

At the end of December 2021, the construction of villa greening, rockery and leisure ponds will begin and will be basically completed in early March 2022.

Fuyuan tea industry

December 27, 2020 Fuyuan Villa lights on

Fuyuan tea industry

From November 2019 to May 2020, the construction of Fuyuan Villa is in full swing

Fuyuan tea industry

On November 12, 2019, the construction of the plant was basically completed.

Fuyuan tea industry

January 27, 2019 The plant has been framed

Fuyuan tea industry

On December 16, 2018, the construction of the factory building and Fuyuan Villa was basically completed.

Fuyuan tea industry

On November 27, 2018, the construction of the house and Fuyuan Villa started.

Fuyuan tea industry

Processing workshop

Fuyuan tea industry

Processing plant